FY04
Submitted by rlbrown on Thu, 2006-06-15 15:13.
Under:
Project Start Date: Fri 1/2/04
Project Finish Date: Mon 10/25/04
Project Finish Date: Mon 10/25/04
STAR FY04 v3 Shutdown
| ID | Name | Duration | Start_Date | Finish_Date | Resource_Names | Predecessors | Successors |
|---|---|---|---|---|---|---|---|
| 1 | STAR Detector Operations | 211.35 days | Mon 1/5/04 | Mon 10/25/04 | |||
| 2 | Physics Run FY04 | 96 days | Mon 1/5/04 | Sat 5/15/04 | 5FF | ||
| 3 | Start Shutdown Activities | 116.35 days | Sat 5/15/04 | Mon 10/25/04 | |||
| 4 | Move Detector into AB | 14.6 days | Sat 5/15/04 | Thu 6/3/04 | |||
| 5 | Purge TPC Gas | 1 day | Sat 5/15/04 | Sat 5/15/04 | 2FF | 6SS | |
| 6 | Subsystem Testing | 6 days | Sat 5/15/04 | Fri 5/21/04 | 5SS | 7 | |
| 7 | Retract PMD Detector | 0.1 days | Mon 5/24/04 | Mon 5/24/04 | Mech.Tech. | 6 | 8 |
| 8 | Remove East BBC Detector | 0.25 days | Mon 5/24/04 | Mon 5/24/04 | Mech.Tech. | 7 | 9 |
| 9 | Retract East Pole Tip | 0.5 days | Mon 5/24/04 | Mon 5/24/04 | Mech.Tech.[2] | 8 | 10FF |
| 10 | Install Scaffold | 0.25 days | Mon 5/24/04 | Mon 5/24/04 | Carpenter[2] | 9FF | 12,11 |
| 11 | Remove Shield Wall | 2.5 days | Mon 5/24/04 | Thu 5/27/04 | Riggers[3] | 10 | 26,23,16SS,18,135 |
| 12 | Remove West Pole Tip Utilities | 0.25 days | Mon 5/24/04 | Tue 5/25/04 | Mech.Tech. | 10 | 13 |
| 13 | Remove West BBC Detector | 0.25 days | Tue 5/25/04 | Tue 5/25/04 | Mech.Tech. | 12 | 14 |
| 14 | Retract West Pole Tip | 0.5 days | Tue 5/25/04 | Tue 5/25/04 | Mech.Tech.[2] | 13 | 15FF |
| 15 | Install Scaffold | 0.13 days | Tue 5/25/04 | Tue 5/25/04 | Carpenter[2] | 14FF | |
| 16 | Disconnect Electrical Power | 0.5 days | Mon 5/24/04 | Tue 5/25/04 | Electrician[2] | 11SS | 18,17 |
| 17 | Disconnect Magnet Power | 0.5 days | Tue 5/25/04 | Tue 5/25/04 | Elect.Tech.[2] | 16 | 18 |
| 18 | Remove Buss Bridge | 0.25 days | Thu 5/27/04 | Thu 5/27/04 | Mech.Tech.[2] | 16,17,11 | 19,21 |
| 19 | Disconnect Platform MCWS | 0.5 days | Thu 5/27/04 | Fri 5/28/04 | Mech.Tech. | 18 | 20 |
| 20 | Disconnect Subsystems Utilities | 1 day | Fri 5/28/04 | Mon 5/31/04 | Mech.Tech. | 19 | 26 |
| 21 | Remove Platform Bridge | 0.25 days | Thu 5/27/04 | Thu 5/27/04 | Mech.Tech.[2] | 18 | 26,22 |
| 22 | Remove South Platform Stairs | 0.25 days | Thu 5/27/04 | Fri 5/28/04 | Mech.Tech.[2] | 21 | 26,24 |
| 23 | Disconnect RHIC Vacuum Pipe | 0.5 days | Thu 5/27/04 | Thu 5/27/04 | Mech.Tech. | 11 | |
| 24 | Remove Seismic Anchors | 0.25 days | Fri 5/28/04 | Fri 5/28/04 | Mech.Tech.[2] | 22 | 25 |
| 25 | Disconnect Magnet LCW | 0.25 days | Fri 5/28/04 | Fri 5/28/04 | Mech.Tech.[2] | 24 | 26 |
| 26 | Roll Detector into AB | 1 day | Mon 5/31/04 | Tue 6/1/04 | Mech.Tech.[2] | 11,21,22,25,20 | 27 |
| 27 | Blow-out Magnet Coils | 0.5 days | Tue 6/1/04 | Tue 6/1/04 | Mech.Tech.[2] | 26 | 28 |
| 28 | Connect South Platform Stairs | 0.5 days | Tue 6/1/04 | Wed 6/2/04 | Mech.Tech.[2] | 27 | 29 |
| 29 | Connect Platform Bridge | 0.5 days | Wed 6/2/04 | Wed 6/2/04 | Mech.Tech.[2] | 28 | 31,30 |
| 30 | Connect Seismic Anchors | 0.5 days | Wed 6/2/04 | Thu 6/3/04 | Mech.Tech. | 29 | |
| 31 | Install Buss Bridge | 0.5 days | Wed 6/2/04 | Thu 6/3/04 | Mech.Tech.[2] | 29 | 32 |
| 32 | Connect Electrical Power | 0.5 days | Thu 6/3/04 | Thu 6/3/04 | Electrician[2] | 31 | 33SS |
| 33 | Connect Subsystems Utilities | 0.5 days | Thu 6/3/04 | Thu 6/3/04 | Mech.Tech. | 32SS | 34SS |
| 34 | Connect Platform MCWS | 0.5 days | Thu 6/3/04 | Thu 6/3/04 | Mech.Tech. | 33SS | 35 |
| 35 | Detector In AB | 0 days | Thu 6/3/04 | Thu 6/3/04 | 34 | 37,117,121 | |
| 36 | Remove East & West FTPC | 13.75 days | Thu 6/3/04 | Wed 6/23/04 | |||
| 37 | Remove E/W IFC Air Manifolds | 0.25 days | Thu 6/3/04 | Thu 6/3/04 | Mech.Tech. | 35 | 38 |
| 38 | Remove East & West Scaffold | 0.5 days | Thu 6/3/04 | Fri 6/4/04 | Carpenter[2] | 37 | 39 |
| 39 | Install West Platform & Rails | 1 day | Fri 6/4/04 | Mon 6/7/04 | Carpenter[2] | 38 | 40,41 |
| 40 | Remove West FTPC | 0.5 days | Mon 6/7/04 | Mon 6/7/04 | Mech.Tech. | 39 | 45 |
| 41 | Rig Installation Frame into AB | 0.5 days | Mon 6/7/04 | Mon 6/7/04 | Riggers[3] | 39 | 42SS |
| 42 | Install East Installation Frame | 0.5 days | Mon 6/7/04 | Mon 6/7/04 | Mech.Tech.[2] | 41SS | 43 |
| 43 | Install East Rails | 1 day | Mon 6/7/04 | Tue 6/8/04 | Mech.Tech.[2] | 42 | 44 |
| 44 | Remove East FTPC | 0.5 days | Tue 6/8/04 | Wed 6/9/04 | Mech.Tech.[2] | 43 | 45 |
| 45 | East & West FTPC's Removed | 0 days | Wed 6/9/04 | Wed 6/9/04 | 40,44 | 46,48 | |
| 46 | Maintenance on FTPC's | 10 days | Wed 6/9/04 | Wed 6/23/04 | Electronic Tech | 45 | |
| 47 | Remove Cone | 11.5 days | Wed 6/9/04 | Thu 6/24/04 | |||
| 48 | Disconnect Utilities | 4 days | Wed 6/9/04 | Tue 6/15/04 | Mech.Tech. | 45 | 49 |
| 49 | Remove Cone from IFC | 0.5 days | Tue 6/15/04 | Tue 6/15/04 | Mech.Tech. | 48 | 76,126 |
| 50 | Remove East Installation Frame | 1 day | Tue 6/22/04 | Wed 6/23/04 | Mech.Tech.[2] | 76,126 | 51FF |
| 51 | Remove Installation Frame from AB | 0.5 days | Wed 6/23/04 | Wed 6/23/04 | Riggers[3] | 50FF | 52 |
| 52 | Remove Installation Frame West | 1 day | Wed 6/23/04 | Thu 6/24/04 | Carpenter[2] | 51 | 53 |
| 53 | Cone Removed | 0 days | Thu 6/24/04 | Thu 6/24/04 | 52 | 57 | |
| 54 | Install East BEMC Modules | 47.5 days | Mon 6/14/04 | Wed 8/18/04 | |||
| 55 | (30) Modules Delivered | 4 days | Mon 6/14/04 | Fri 6/18/04 | Riggers[3] | 57FF-5 days | 56FF |
| 56 | (30) Modules Staged in AB | 4 days | Mon 6/14/04 | Fri 6/18/04 | Mech.Tech.[2] | 55FF | |
| 57 | Install East & West Scaffold | 0.5 days | Thu 6/24/04 | Fri 6/25/04 | Carpenter[2] | 53 | 58,55FF-5 days |
| 58 | Remove East Side Cables & Tray | 3 days | Fri 6/25/04 | Wed 6/30/04 | Mech.Tech.[2] | 57 | 59 |
| 59 | Erect Installation Fixture S.E. Upper | 0.5 days | Wed 6/30/04 | Wed 6/30/04 | Mech.Tech.[2] | 58 | 60 |
| 60 | Remove S.E. TPC Support Arm | 0.25 days | Wed 6/30/04 | Thu 7/1/04 | Mech.Tech.[2] | 59 | 61 |
| 61 | Install Modules 106-103 | 4 days | Thu 7/1/04 | Wed 7/7/04 | Mech.Tech.[2] | 60 | 62 |
| 62 | Erect Installation Fixture S.E. Lower | 0.5 days | Wed 7/7/04 | Wed 7/7/04 | Mech.Tech.[2] | 61 | 63 |
| 63 | Install Modules 102-89 | 14 days | Wed 7/7/04 | Tue 7/27/04 | Mech.Tech.[2] | 62 | 64 |
| 64 | Install S.E. TPC Support Arm | 0.5 days | Tue 7/27/04 | Wed 7/28/04 | Mech.Tech.[2] | 63 | 65 |
| 65 | Erect Installation Fixture N.E. Lower | 0.5 days | Wed 7/28/04 | Wed 7/28/04 | Mech.Tech.[2] | 64 | 66 |
| 66 | Install Modules 77-88 | 12 days | Wed 7/28/04 | Fri 8/13/04 | Mech.Tech.[2] | 65 | 67 |
| 67 | Remove Installation Fixture | 0.25 days | Fri 8/13/04 | Fri 8/13/04 | Mech.Tech.[2] | 66 | 68 |
| 68 | Install East Side Cables & Tray | 3 days | Fri 8/13/04 | Wed 8/18/04 | Mech.Tech.[2] | 67 | 69 |
| 69 | East BEMC Installation Complete | 0 days | Wed 8/18/04 | Wed 8/18/04 | 68 | 82,72 | |
| 70 | Install BEMC PMT Boxes | 35 days | Wed 7/14/04 | Wed 9/1/04 | |||
| 71 | Install 208 VAC Power | 15 days | Wed 7/14/04 | Wed 8/4/04 | Electrician[2] | 72SF-10 days | |
| 72 | Install PMT Boxes | 10 days | Wed 8/18/04 | Wed 9/1/04 | Mech.Tech.[2] | 69 | 73FF,71SF-10 days |
| 73 | Install Electronics | 20 days | Wed 8/4/04 | Wed 9/1/04 | Electronic Tech | 72FF | 74 |
| 74 | PMT Box Installation Complete | 0 days | Wed 9/1/04 | Wed 9/1/04 | 73 | 144 | |
| 75 | Install SSD | 20.5 days | Tue 6/15/04 | Wed 7/14/04 | |||
| 76 | Rig Cone to Cleanroom Roof | 0.5 days | Tue 6/15/04 | Wed 6/16/04 | Mech.Tech. | 49 | 77,50 |
| 77 | Install SSD on Cone | 20 days | Wed 6/16/04 | Wed 7/14/04 | Mech.Tech. | 76 | 78SS,80 |
| 78 | Install LV Crate & Cables | 5 days | Wed 6/16/04 | Wed 6/23/04 | Electronic Tech | 77SS | 79 |
| 79 | Install RDO Boxes | 5 days | Wed 6/23/04 | Wed 6/30/04 | Electronic Tech | 78 | |
| 80 | SSD Installed on Cone | 0 days | Wed 7/14/04 | Wed 7/14/04 | 77 | 85 | |
| 81 | Install Cone | 20.5 days | Wed 8/18/04 | Thu 9/16/04 | |||
| 82 | Rig Installation Frame into AB | 0.5 days | Wed 8/18/04 | Thu 8/19/04 | Riggers[3] | 69 | 83SS |
| 83 | Install East Installation Frame | 0.5 days | Wed 8/18/04 | Thu 8/19/04 | Mech.Tech.[2] | 82SS | 84 |
| 84 | Install Tables & Rails | 0.5 days | Thu 8/19/04 | Thu 8/19/04 | Mech.Tech. | 83 | 85 |
| 85 | Rig Cone to Rails | 0.5 days | Thu 8/19/04 | Fri 8/20/04 | Mech.Tech.[2] | 84,80 | 86 |
| 86 | Survey SSD to SVT | 2 days | Fri 8/20/04 | Tue 8/24/04 | Surveyors[2] | 85 | 87 |
| 87 | Complete SSD Installation | 2 days | Tue 8/24/04 | Thu 8/26/04 | Mech.Tech. | 86 | 88 |
| 88 | Test Utility Connections | 1 day | Thu 8/26/04 | Fri 8/27/04 | Electronic Tech | 87 | 89FF |
| 89 | Clean TPC IFC | 1 day | Thu 8/26/04 | Fri 8/27/04 | Mech.Tech. | 88FF | 90 |
| 90 | Install Cone in Detector | 0.5 days | Fri 8/27/04 | Fri 8/27/04 | Mech.Tech. | 89 | 91 |
| 91 | Test IFC High Voltage | 0.5 days | Fri 8/27/04 | Mon 8/30/04 | Electronic Tech | 90 | 92 |
| 92 | Survey TPC to Magnet | 2 days | Mon 8/30/04 | Wed 9/1/04 | Surveyors[2] | 91 | 93 |
| 93 | Survey SVT to TPC | 2 days | Wed 9/1/04 | Fri 9/3/04 | Surveyors[2] | 92 | 94 |
| 94 | Install East Partitions | 0.5 days | Fri 9/3/04 | Fri 9/3/04 | Mech.Tech. | 93 | 110 |
| 95 | Connect Water Lines | 0.5 days | Mon 9/6/04 | Tue 9/7/04 | Mech.Tech. | 110 | 96 |
| 96 | Connect RDO Cables | 1 day | Tue 9/7/04 | Wed 9/8/04 | Electronic Tech | 95 | 97 |
| 97 | Remove East Rails from IFC | 0.5 days | Wed 9/8/04 | Wed 9/8/04 | Mech.Tech.[2] | 96 | 98 |
| 98 | Remove East Installation Frame | 0.5 days | Wed 9/8/04 | Thu 9/9/04 | Mech.Tech.[2] | 97 | 99FF |
| 99 | Remove Installation Frame from AB | 0.25 days | Thu 9/9/04 | Thu 9/9/04 | Riggers[3] | 98FF | 100 |
| 100 | East Side Complete | 0 days | Thu 9/9/04 | Thu 9/9/04 | 99 | 107,101 | |
| 101 | Install West Partitions | 0.5 days | Thu 9/9/04 | Thu 9/9/04 | Mech.Tech. | 100 | 112 |
| 102 | Connect Water Lines | 0.5 days | Mon 9/13/04 | Mon 9/13/04 | Mech.Tech. | 114 | 103 |
| 103 | Connect RDO Cables | 1 day | Mon 9/13/04 | Tue 9/14/04 | Electronic Tech | 102 | 104 |
| 104 | Remove West Rails from IFC | 0.5 days | Tue 9/14/04 | Wed 9/15/04 | Mech.Tech. | 103 | 105 |
| 105 | Remove Installation Frame West | 1 day | Wed 9/15/04 | Thu 9/16/04 | Carpenter[2] | 104 | 106 |
| 106 | West Side Complete | 0 days | Thu 9/16/04 | Thu 9/16/04 | 105 | 107 | |
| 107 | Cone Installation Complete | 0 days | Thu 9/16/04 | Thu 9/16/04 | 100,106 | 144 | |
| 108 | Install FTPC East & West in AB | 12.5 days | Wed 8/25/04 | Mon 9/13/04 | |||
| 109 | Run & Test N. Platform | 5 days | Wed 8/25/04 | Wed 9/1/04 | Electronic Tech | 110SF-2 days | |
| 110 | Install East FTPC in Detector | 1 day | Fri 9/3/04 | Mon 9/6/04 | Mech.Tech.[2] | 94 | 115,109SF-2 days,95 |
| 111 | Run & Test N. Platform | 5 days | Wed 9/1/04 | Wed 9/8/04 | Electronic Tech | 114SF-2 days | |
| 112 | Remove West Scaffold | 0.25 days | Thu 9/9/04 | Fri 9/10/04 | Carpenter[2] | 101 | 113 |
| 113 | Install West Platform & Rails | 0.25 days | Fri 9/10/04 | Fri 9/10/04 | Carpenter[2] | 112 | 114 |
| 114 | Install West FTPC in Detector | 1 day | Fri 9/10/04 | Mon 9/13/04 | Mech.Tech.[2] | 113 | 115,111SF-2 days,102 |
| 115 | FTPC Installed in AB | 0 days | Mon 9/13/04 | Mon 9/13/04 | 114,110 | ||
| 116 | PMD Maintenance | 40 days | Thu 6/3/04 | Thu 7/29/04 | |||
| 117 | Subsystem Maintenance | 30 days | Thu 6/3/04 | Thu 7/15/04 | 35 | 118 | |
| 118 | Detector Commisioning | 10 days | Thu 7/15/04 | Thu 7/29/04 | 117 | 119 | |
| 119 | PMD Maintenance Complete | 0 days | Thu 7/29/04 | Thu 7/29/04 | 118 | ||
| 120 | EEMC Maintenance | 90 days | Thu 6/3/04 | Thu 10/7/04 | |||
| 121 | Maintenance | 50 days | Thu 6/3/04 | Thu 8/12/04 | 35 | 122SS | |
| 122 | MAPMT Installation | 80 days | Thu 6/3/04 | Thu 9/23/04 | Mech.Tech.[2] | 121SS | 123 |
| 123 | Subsystem Testing | 10 days | Thu 9/23/04 | Thu 10/7/04 | 122 | 124 | |
| 124 | EEMC Maintenance Complete | 0 days | Thu 10/7/04 | Thu 10/7/04 | 123 | ||
| 125 | TPC Maintenance | 50 days | Tue 6/15/04 | Tue 8/24/04 | |||
| 126 | Repair IFC Strip Short | 5 days | Tue 6/15/04 | Tue 6/22/04 | Mech.Tech. | 49 | 127,50,131SS |
| 127 | Modify Resistor Chain | 5 days | Tue 6/22/04 | Tue 6/29/04 | Mech.Tech. | 126 | 128 |
| 128 | FEE & RDO Maintenance | 40 days | Tue 6/29/04 | Tue 8/24/04 | Electronic Tech | 127 | 129 |
| 129 | TPC Maintenance Complete | 0 days | Tue 8/24/04 | Tue 8/24/04 | 128 | ||
| 130 | TOF Maintenance | 15 days | Tue 6/15/04 | Tue 7/6/04 | |||
| 131 | Tray Maintenance | 10 days | Tue 6/15/04 | Tue 6/29/04 | 126SS | 132 | |
| 132 | Detector Testing | 5 days | Tue 6/29/04 | Tue 7/6/04 | 131 | 133 | |
| 133 | TOFp Maintenance Complete | 0 days | Tue 7/6/04 | Tue 7/6/04 | 132 | ||
| 134 | FPD Installation | 20 days | Thu 5/27/04 | Thu 6/24/04 | |||
| 135 | Install West Detectors | 10 days | Thu 5/27/04 | Thu 6/10/04 | Mech.Tech. | 11 | 136 |
| 136 | Install N. E. Stand for 20-cm Travel | 5 days | Thu 6/10/04 | Thu 6/17/04 | Mech.Tech.[2] | 135 | 137 |
| 137 | Detector Commisioning | 5 days | Thu 6/17/04 | Thu 6/24/04 | 136 | 138 | |
| 138 | FPD Installation Complete | 0 days | Thu 6/24/04 | Thu 6/24/04 | 137 | 140 | |
| 139 | BBC Maintenance | 15 days | Thu 6/24/04 | Thu 7/15/04 | |||
| 140 | Subsystem Maintenance | 10 days | Thu 6/24/04 | Thu 7/8/04 | 138 | 141 | |
| 141 | Detector Commisioning | 5 days | Thu 7/8/04 | Thu 7/15/04 | 140 | 142 | |
| 142 | BBC Maintenance Complete | 0 days | Thu 7/15/04 | Thu 7/15/04 | 141 | ||
| 143 | Move Detector into WAH | 27 days | Thu 9/16/04 | Mon 10/25/04 | |||
| 144 | Disconnect Electrical Power | 0.5 days | Thu 9/16/04 | Thu 9/16/04 | Electrician[2] | 107,74 | 147,145SS,146SS |
| 145 | Disconnect Platform MCWS | 0.5 days | Thu 9/16/04 | Thu 9/16/04 | Mech.Tech. | 144SS | |
| 146 | Disconnect TPC Utilities | 0.5 days | Thu 9/16/04 | Thu 9/16/04 | Mech.Tech. | 144SS | |
| 147 | Remove Buss Bridge | 0.5 days | Thu 9/16/04 | Fri 9/17/04 | Mech.Tech.[2] | 144 | 148 |
| 148 | Remove Platform Bridge | 0.5 days | Fri 9/17/04 | Fri 9/17/04 | Mech.Tech.[2] | 147 | 149 |
| 149 | Remove South Platform Stairs | 1 day | Fri 9/17/04 | Mon 9/20/04 | Mech.Tech.[2] | 148 | 150 |
| 150 | Disconnect Seismic Anchors | 0.5 days | Mon 9/20/04 | Tue 9/21/04 | Mech.Tech.[2] | 149 | 151SS |
| 151 | Lower Detector to Rails | 0.5 days | Mon 9/20/04 | Tue 9/21/04 | Mech.Tech.[2] | 150SS | 152 |
| 152 | Roll Detector into WAH | 1.5 days | Tue 9/21/04 | Wed 9/22/04 | Mech.Tech.[2] | 151 | 153,154 |
| 153 | Connect Magnet LCW | 1 day | Wed 9/22/04 | Thu 9/23/04 | Mech.Tech.[2] | 152 | |
| 154 | Raise/Level Detector @ IR | 0.5 days | Wed 9/22/04 | Thu 9/23/04 | Mech.Tech.[2] | 152 | 155FF,163 |
| 155 | Connect Seismic Anchors | 0.5 days | Wed 9/22/04 | Thu 9/23/04 | Mech.Tech.[2] | 154FF | 159,156 |
| 156 | Install Buss Bridge | 0.5 days | Thu 9/23/04 | Thu 9/23/04 | Mech.Tech.[2] | 155 | 157,160 |
| 157 | Connect Electrical Power | 1 day | Thu 9/23/04 | Fri 9/24/04 | Electrician[2] | 156 | 158 |
| 158 | Connect Magnet Power | 1 day | Fri 9/24/04 | Mon 9/27/04 | Elect.Tech.[2] | 157 | |
| 159 | Connect All Subsystem Utilities | 2 days | Thu 9/23/04 | Mon 9/27/04 | Mech.Tech.[2] | 155 | 168,166 |
| 160 | Connect Platform MCWS | 0.5 days | Thu 9/23/04 | Fri 9/24/04 | Mech.Tech. | 156 | 168,161 |
| 161 | Connect South Platform Stairs | 1 day | Fri 9/24/04 | Mon 9/27/04 | Mech.Tech.[2] | 160 | 162 |
| 162 | Connect Platform Bridge | 0.5 days | Mon 9/27/04 | Mon 9/27/04 | Mech.Tech.[2] | 161 | 167 |
| 163 | Connect Vacuum Pipe & Supports | 0.5 days | Thu 9/23/04 | Thu 9/23/04 | Mech.Tech.[2] | 154 | 164 |
| 164 | Vacuum Pipe Bake-out | 5 days | Thu 9/23/04 | Thu 9/30/04 | Mech.Tech.[2] | 163 | 165 |
| 165 | Survey Beam Pipe & Magnet | 4 days | Thu 9/30/04 | Wed 10/6/04 | Surveyors[2] | 164 | |
| 166 | Detector Safety Certification | 2 days | Mon 9/27/04 | Wed 9/29/04 | 159 | ||
| 167 | Install Shield Wall | 3 days | Mon 9/27/04 | Thu 9/30/04 | Riggers[3] | 162 | 171 |
| 168 | Subsystems testing in WAH | 20 days | Mon 9/27/04 | Mon 10/25/04 | 160,159 | 169SS+5 days | |
| 169 | Install Pole Tips | 2 days | Mon 10/4/04 | Wed 10/6/04 | Mech.Tech.[2] | 168SS+5 days | 170 |
| 170 | Install BBC Detectors | 1 day | Wed 10/6/04 | Thu 10/7/04 | Mech.Tech.[2] | 169 | 171 |
| 171 | Shutdown Activities Complete | 0 days | Thu 10/7/04 | Thu 10/7/04 | 167,170 |