Straw-man QM02 production plan
(Assuming no new calibrations show-stoppers) plan to
migrate NEW ? PRO and begin QM02 production ~18 Feb
(? just 19 weeks for production until end of 1 July)
hope/desire homogeneous production (consistent reco software) for full production
Use Jerome’s numbers for production rate (real time)…
Au200Au central 0.38 Mevts/wk
Au200Au minbias 1.4 Mevts/wk (*)
pp minbias 4.2 Mevts/wk (**)
… and stats requirements for desired physics to estimate overall time
(*) x 0.7 if MinBiasVertex instead of ProductionMinBias
(**) assumes 60% usable events