- Shut Down Plan


TO DO LIST at the end of the RUN 7

Around June 26th (end of the RUN), need to:
  1. Pulser runs (done)
  2. Raw data runs (done)
  3. Monitor the temperature for 2-3 hours (done)
When possible:
  1. Look at the cooling lines (Artemios and Micheal)
  2. RDO tests with optical power meter (Micheal and Bob) (results)

Run plan for removal of the SSD, testing and storage starting July 29

Tests by Stephane and Christophe (Week of September 25th 2007)