Next: Stop any runs
Up: MiniDAQ instructions
Previous: MiniDAQ code
Setting Up the Test Sector Hardware
Locate the NIM bins which contain the HV power supplies, BNC tail pulser,
etc. and check the settings on the units in these racks.
-
The BNC Tail Pulser settings should be:
-
External trigger
-
Single pulse
-
Maximum delay on 10 microsecond scale
-
Internal reference
-
+ Polarity
-
0.05 microsecond rise time
-
Maximum amplitude
-
1000 microsecond fall time
-
No attenuation
-
The drift-field voltage should be on for all data taking.
Check it by plugging a DVM into the voltage monitor
lemo jack of the peach-colored NIM HV unit (Chan. A); be sure you
don't get the current monitor jack by mistake. The voltage will be
displayed in kilovolts. If the voltage is unreasonable, be sure that the
cable and connector are not damaged, giving an open circuit.
-
Outer sector: 1.389 kV
-
Inner sector: 1.584 kV
If the HV supply is not on, set the vernier dial to 0 V and the
toggle switch to ``auto reset;'' now, switch it on and set to ``trip hold.''
Raise the voltage slowly, being careful not to exceed the current limit
(80Lock the vernier knob.
-
The gating grid voltage supply should also be on for all data taking.
It should be set to -90 volts for both outer and inner subsectors.
Lock the vernier knob.
-
The anode-wire voltage should be on only for cosmic-ray or laser runs.
Check this on the red NIM HV unit (Chan. A) by plugging a DVM
into the voltage monitor lemo jack; be sure you don't get the current
monitor jack by mistake. The voltage will be displayed in kilovolts.
If the voltage is unreasonable, be sure that the
cable and connector are not damaged, giving an open circuit.
-
Outer sector: 1.450 kV
-
Inner sector: 1.171 kV
If the HV supply is not on, set the vernier dial to 0 V and the
toggle switch to ``auto reset;'' now, switch it on and set to ``trip hold.''
Raise the voltage slowly, being careful not to exceed the current limit
(80Lock the vernier knob.
-
On the Neslab chiller (large, yellowish, stand-alone unit):
turn on the chiller with rocker switch, then check that the flow valve
is open enough that the blue, interlocked, control-power lights
on the low-voltage power supplies are illuminated. Increase the flow
a bit past the point where they illuminate.
-
There is one Kepco low-voltage power supply per readout board; the supplies
are mounted in 19'' racks in groups of three.
Supplies 1 and 2 are for the inner sector;
units 3, 4, 5 and 6 are for the outer sector. Check the number on the
power cable, if in doubt.
Use Slow Controls to set the needed Kepco low-voltage power supplies
to ``on;'' if necessary, one can also set them to ``local'' for manual
control.
-
For cosmic-ray runs, the HV PMT power supply at the top of the trigger rack
must be set to -1700 V, with both power switches set to ``on.''
(Both pilot lights are dead; look at the HV meter (but even the HV meter
has occasionally had problems!)
-
For cosmic-ray runs, the two scintillator counters should be centered
in the drift direction over the laser windows, visible at the top and
bottom of the sector frame. Usually, the lower counter has 2 inches
of lead over its sensitive area, so as to trigger only on high-momentum
cosmics (200 MeV/c muons).
-
The OR'ed busy from the Rosie's must be wired manually. All Rosie's
enabled in the Run Control ``configuration'' window busies must be included
in the OR, and only these. Check that it is wired correctly. The cables
are labeled 1-6, the same as the Rosies. (Strictly speaking,
no particular relationship is required between readout board and Rosie
numbering.)
Procedures are different to set up a laser run.
Written: October 3, 1996 by R.Bossingham
Last modified: July 8, 1997 by R.Bossingham
Page maintenance:
Roy Bossingham, LBNL
RRBossingham@lbl.gov