|
T963 Details:
T963 program which takes the advantage of
Meson Test-Beam Facility at
FNAL is located in MT6, see Fig 1&2. The
facility can provide charged particle
beam such as Muon, Pion and Proton from
1GeV to 120GeV.
 |
|
 |
|
Fig1:
Airscape of Test-Beam
Facilities (see here) |
|
Fig2:
MT6 outlook (see
here) |
|
|
|
|
A
layout of the Meson Lab, MTest beamline elements and MTest user
areas can be found :
- MTest User
Areas Rough Outline (jpeg,ppt)
- Meson Lab
Drawings
(pdf)
(ps)
- Meson Lab
Autocad file
(AutoCad)
(IDEAS)
- MTest User
Areas with radiation survey data (ps)
- MTest
Beamline Elements (pdf)
- All SY120
Beamline Elements (pdf)
- Electrical
system at Mtest (pdf)
More detail on the facility recommended see
here.
T963 Detectors Layout:
Fig 3 displays a detailed drawing where T963 is located in the
main experiment hall. The blue area shows where the DAQ room and control
room are. The green colored area points out where the motive platform
is. It is used to support two Large Area MRPCs and makes it easily to
perform spacial resolution scan. T963 detectors layout can be found in
Fig 4, it shows the geometrical distribution of two TOF scintillators, nine MWPC wire chambers,
two MRPC chambers and three GEM chambers along the beam line.
 |
|
 |
|
Fig 3:
T963 ichnography at MT6 (see here) |
|
Fig 4:
T963 detectors layout (see here,
doc) |
|
|
|
|
Module Definition:
Modules are defined as
MODULE #1 (built
at Tsinghua Univ., white tray box) and
MODULE #2 (built
at USTC, silver tray box) along the beam insert direction.
Installation Details:
From April 26th, detector installations
has begun in the MT6 areas. Fig 5 shows that the MRPCs were installed on
the movable platform and began to flow gas. The photograph was taken from the High Voltage
side. Due to MODULE #2 has a thicker try box than MODULE #2, it was
installed behind the latter along the beam line direction. In Fig 6,
three GEMs were fixed between MRPC modules and TOF2 towards north. Both
the pictures
were taken just when GEMs high voltage was applied on April 30th, 2007.
 |
|
 |
|
Fig 5:
MRPCs were installed (see here) |
|
Fig 6:
GEM high voltage applied (see here) |
|
|
|
|
Beam running:
High voltage is applied to MODULE #1 7,300V and
MODULE #2 6,300V. Table 1 shows that #2
has a higher high voltage dark current than #1, for both cathode
and anode. We estimated that compared with #1, #2
relatively had a lower resistance and weaker static electric field
generated by collecting ionized electron and ion pairs. The maxim values
in the table were recoded when the detectors were working on the beam
spills, while minimum were stable and in the same value as dumping. Fig 7
shows HV crate is under the working status. In Fig 8, it shows the experimental areas
were isolated when beam is running.
Table 1: HV Dark Current |
|
|
+HV Dark current (max) |
-HV Dark current (max) |
+HV Dark current (min) |
-HV Dark current (min) |
MODULE #1 |
+ 190 nA |
- 140 nA |
+ 40nA |
- 30 nA |
MODULE #2 |
+ 330 nA |
- 340 nA |
+ 100 nA |
- 30 nA |
|
 |
|
 |
|
Fig 7:
HV crate working status (see here) |
|
Fig 8:
Beam Area Enclosed (see here) |
|
|
|
|
|
|