Work Planned

Under:
Based on:
  • An initial meeting held during QM06 (Chair: J.Lauret, L. Barnby, O, Baranikova, A. Rose)
  • Email exchange and notes from the meeting (From: J. Lauret, Date: 11/20/2006 22:36, Subject: Summary of our embedding meeting)
  • Further EMails from L. Barnby in embedding-hn (Date: 1/18/2007 15:12, Thread ID 84)
the following task list has been defined.

ID
Task
% CompleteDurationStartFinishAssigned people
1
General QA consolidation
28%109 days?Thu 11/16/06Tue 4/17/07 
2      
3
Documentation
25%37 daysMon 12/18/06Tue 2/6/07 
4
Port old QA documentation to Drupal, define hierarchy
50%4 wksMon 12/18/06Fri 1/12/07Cristina Suarez[10%]
5
Add general documentation descriptive of the embedding purpose
0%2 daysMon 1/15/07Tue 1/16/07Lee Barnby[10%],Andrew Rose[10%]
6
Add documentation as per the embedding procedure, diverse embedding
0%2 daysMon 1/15/07Tue 1/16/07Lee Barnby[10%],Andrew Rose[10%]
7
Import PDSF documentation into Drupal
0%1 wkWed 1/17/07Tue 1/23/07Andrew Rose[10%]
8
Review and adjust documentation
0%1 wkWed 1/24/07Tue 1/30/07Olga Barranikova[10%],Andrew Rose[5%],Lee Barnby[5%]
9
Deliver documentation to collaboration for comments
0%1 wkWed 1/31/07Tue 2/6/07STAR Collaboration[10%]
10
Drop all old documentation, adjust link (redirect)
0%1 dayWed 1/31/07Wed 1/31/07Andrew Rose[15%],Jerome Lauret[15%]
11      
12
Line of authority, base conventions
84%52 daysThu 11/16/06Fri 1/26/07 
13
Meeting with key personnel
100%1 dayThu 11/16/06Thu 11/16/06Jerome Lauret[10%],Olga Barranikova[10%],Andrew Rose[10%],Lee Barnby[10%]
14
Define responsibilities and scope of diverse individual in the embedding team
100%1 monMon 12/4/06Fri 12/29/06Jerome Lauret[15%],Olga Barranikova[6%]
15
Define file name convention, document final proposal
50%2 wksMon 1/15/07Fri 1/26/07Jerome Lauret[6%],Lee Barnby[6%],Lidia Didenko[6%],Andrew Rose[6%]
16      
17
Collaborative work
45%60 daysMon 1/22/07Fri 4/13/07 
18
General Cataloguing issues
0%9 daysMon 1/29/07Thu 2/8/07 
19
Test Catalog registration, adjust as necessary
0%4 daysMon 1/29/07Thu 2/1/07Lidia Didenko[20%],Jerome Lauret[20%]
20
Extend Spider/Indexer to include embedding registration
0%1 wkFri 2/2/07Thu 2/8/07Jerome Lauret[10%]
21
Bug tracking, mailing lists and other tools
69%60 daysMon 1/22/07Fri 4/13/07 
22
Re-enable embedding list, establish focus comunication at PWG level and user level
75%3 monsMon 1/22/07Fri 4/13/07Jerome Lauret[10%]
23
Establish embedding RT system queue
0%1 dayTue 1/23/07Tue 1/23/07Jerome Lauret[5%]
24
Exercise embedding RT queue, adjust requirement
0%4 daysWed 1/24/07Mon 1/29/07Andrew Rose[10%]
25
Establish data transfer scheme to a BNL disk pool
0%22 daysMon 1/22/07Tue 2/20/07 
26
Define requirements, general problems and issues
0%1 wkMon 1/22/07Fri 1/26/07 
27
Add data pool mechanism at BNL, transfer with any method
0%1 wkMon 1/29/07Fri 2/2/07 
28
Establish security schem, HPSS auto-synching
0%1 wkMon 2/5/07Fri 2/9/07 
29
Test on one or more sites (non-PDSF)
0%1 wkMon 2/12/07Fri 2/16/07 
30
Integrate to all participating sites
0%1 wkMon 2/12/07Fri 2/16/07 
31
Document data transfer schemeand procedure
0%2 daysMon 2/19/07Tue 2/20/07 
32      
33
CVS check-in and cleanup
4%17 days?Mon 1/22/07Tue 2/13/07 
34
Initial setup, existing framework
0%17 daysMon 1/22/07Tue 2/13/07 
35
Define proper CVS location for perl, libs, macros
0%1 dayMon 1/22/07Mon 1/22/07Jerome Lauret[10%],Andrew Rose[10%],Lee Barnby[10%]
36
Add existing QA macros to CVS
0%1 dayTue 1/23/07Tue 1/23/07Andrew Rose[20%]
37
Checkout and test on +1 site (non-PDSF), adjust as necessary
0%1 wkWed 1/24/07Tue 1/30/07Lee Barnby[10%]
38
Bootstrap on +1 site / remove ALL site specifics references
0%1 wkWed 1/31/07Tue 2/6/07Cristina Suarez[10%]
39
Commit to CVS, verify new scripts on all sites, final adjustments
0%1 wkWed 2/7/07Tue 2/13/07Cristina Suarez[10%],Andrew Rose[10%],Lee Barnby[10%]
40
QA and nightly tests
17%7 days?Mon 1/22/07Tue 1/30/07 
41
Establish a QA area in CVS
100%1 day?Mon 1/22/07Mon 1/22/07 
42
Check existing QA suite
0%1 wkWed 1/24/07Tue 1/30/07 
43      
44
Development
0%62 daysMon 1/22/07Tue 4/17/07 
45
General QA consolidation
0%10 daysWed 1/31/07Tue 2/13/07 
46
Gather feedback from PWG, add QA tests relevant to Physics topics
0%2 wksWed 1/31/07Tue 2/13/07 
47
Establish nightly test framework at BNL for embedding
0%1 wkWed 1/31/07Tue 2/6/07 
48
General improvements
0%35 daysMon 1/22/07Fri 3/9/07 
49
Requirements study for an embedding request interface
0%2 wksMon 1/29/07Fri 2/9/07Andrew Rose[10%],Jerome Lauret[10%]
50
Develop new embedding request form compatible with Drupal module
0%4 wksMon 2/12/07Fri 3/9/07Andrew Rose[10%]
51
Test new interface, import old tasks (historical purposes)
0%5 daysMon 1/22/07Fri 1/26/07Andrew Rose[10%],Cristina Suarez[10%]
52
Distributed Computing
0%20 daysWed 2/14/07Tue 3/13/07 
53
Use SUMS framework to submit embedding, establish first XML
0%1 wkWed 2/14/07Tue 2/20/07Lee Barnby[10%]
54
Test on one site
0%1 wkWed 2/21/07Tue 2/27/07Lee Barnby[10%]
55
Test on all sites, adjust as necessary
0%2 wksWed 2/28/07Tue 3/13/07Cristina Suarez[10%],Andrew Rose[10%],Lee Barnby[10%]
56
Gridfication
0%25 daysWed 3/14/07Tue 4/17/07 
57
Test XML using Grid policy (one site)
0%1 wkWed 3/14/07Tue 3/20/07 
58
Establish test of data transfer method, GSI enabled HPSS access possible
0%1 wkWed 3/21/07Tue 3/27/07 
59
Regression and stress test on one site
0%1 wkWed 3/28/07Tue 4/3/07 
60
Test on +1 site, infrastructure consolidation
0%2 wksWed 4/4/07Tue 4/17/07 
61      
62
Embedding operation
25%261 days?Mon 1/1/07Mon 12/31/07 
63
PDSF support
50%261 days?Mon 1/1/07Mon 12/31/07Andrew Rose[10%]
64
BHAM support
10%261 days?Mon 1/1/07Mon 12/31/07Lee Barnby[10%]
65
UIC Support including QA
15%261 days?Mon 1/1/07Mon 12/31/07Olga Barranikova[5%],Cristina Suarez[10%]