Work Planned
Submitted by jeromel on Tue, 2006-12-26 19:57.
Under:
Based on:
- An initial meeting held during QM06 (Chair: J.Lauret, L. Barnby, O, Baranikova, A. Rose)
- Email exchange and notes from the meeting (From: J. Lauret, Date: 11/20/2006 22:36, Subject: Summary of our embedding meeting)
- Further EMails from L. Barnby in embedding-hn (Date: 1/18/2007 15:12, Thread ID 84)
| ID | Task | % Complete | Duration | Start | Finish | Assigned people |
|---|---|---|---|---|---|---|
| 1 | General QA consolidation | 28% | 109 days? | Thu 11/16/06 | Tue 4/17/07 | |
| 2 | ||||||
| 3 | Documentation | 25% | 37 days | Mon 12/18/06 | Tue 2/6/07 | |
| 4 | Port old QA documentation to Drupal, define hierarchy | 50% | 4 wks | Mon 12/18/06 | Fri 1/12/07 | Cristina Suarez[10%] |
| 5 | Add general documentation descriptive of the embedding purpose | 0% | 2 days | Mon 1/15/07 | Tue 1/16/07 | Lee Barnby[10%],Andrew Rose[10%] |
| 6 | Add documentation as per the embedding procedure, diverse embedding | 0% | 2 days | Mon 1/15/07 | Tue 1/16/07 | Lee Barnby[10%],Andrew Rose[10%] |
| 7 | Import PDSF documentation into Drupal | 0% | 1 wk | Wed 1/17/07 | Tue 1/23/07 | Andrew Rose[10%] |
| 8 | Review and adjust documentation | 0% | 1 wk | Wed 1/24/07 | Tue 1/30/07 | Olga Barranikova[10%],Andrew Rose[5%],Lee Barnby[5%] |
| 9 | Deliver documentation to collaboration for comments | 0% | 1 wk | Wed 1/31/07 | Tue 2/6/07 | STAR Collaboration[10%] |
| 10 | Drop all old documentation, adjust link (redirect) | 0% | 1 day | Wed 1/31/07 | Wed 1/31/07 | Andrew Rose[15%],Jerome Lauret[15%] |
| 11 | ||||||
| 12 | Line of authority, base conventions | 84% | 52 days | Thu 11/16/06 | Fri 1/26/07 | |
| 13 | Meeting with key personnel | 100% | 1 day | Thu 11/16/06 | Thu 11/16/06 | Jerome Lauret[10%],Olga Barranikova[10%],Andrew Rose[10%],Lee Barnby[10%] |
| 14 | Define responsibilities and scope of diverse individual in the embedding team | 100% | 1 mon | Mon 12/4/06 | Fri 12/29/06 | Jerome Lauret[15%],Olga Barranikova[6%] |
| 15 | Define file name convention, document final proposal | 50% | 2 wks | Mon 1/15/07 | Fri 1/26/07 | Jerome Lauret[6%],Lee Barnby[6%],Lidia Didenko[6%],Andrew Rose[6%] |
| 16 | ||||||
| 17 | Collaborative work | 45% | 60 days | Mon 1/22/07 | Fri 4/13/07 | |
| 18 | General Cataloguing issues | 0% | 9 days | Mon 1/29/07 | Thu 2/8/07 | |
| 19 | Test Catalog registration, adjust as necessary | 0% | 4 days | Mon 1/29/07 | Thu 2/1/07 | Lidia Didenko[20%],Jerome Lauret[20%] |
| 20 | Extend Spider/Indexer to include embedding registration | 0% | 1 wk | Fri 2/2/07 | Thu 2/8/07 | Jerome Lauret[10%] |
| 21 | Bug tracking, mailing lists and other tools | 69% | 60 days | Mon 1/22/07 | Fri 4/13/07 | |
| 22 | Re-enable embedding list, establish focus comunication at PWG level and user level | 75% | 3 mons | Mon 1/22/07 | Fri 4/13/07 | Jerome Lauret[10%] |
| 23 | Establish embedding RT system queue | 0% | 1 day | Tue 1/23/07 | Tue 1/23/07 | Jerome Lauret[5%] |
| 24 | Exercise embedding RT queue, adjust requirement | 0% | 4 days | Wed 1/24/07 | Mon 1/29/07 | Andrew Rose[10%] |
| 25 | Establish data transfer scheme to a BNL disk pool | 0% | 22 days | Mon 1/22/07 | Tue 2/20/07 | |
| 26 | Define requirements, general problems and issues | 0% | 1 wk | Mon 1/22/07 | Fri 1/26/07 | |
| 27 | Add data pool mechanism at BNL, transfer with any method | 0% | 1 wk | Mon 1/29/07 | Fri 2/2/07 | |
| 28 | Establish security schem, HPSS auto-synching | 0% | 1 wk | Mon 2/5/07 | Fri 2/9/07 | |
| 29 | Test on one or more sites (non-PDSF) | 0% | 1 wk | Mon 2/12/07 | Fri 2/16/07 | |
| 30 | Integrate to all participating sites | 0% | 1 wk | Mon 2/12/07 | Fri 2/16/07 | |
| 31 | Document data transfer schemeand procedure | 0% | 2 days | Mon 2/19/07 | Tue 2/20/07 | |
| 32 | ||||||
| 33 | CVS check-in and cleanup | 4% | 17 days? | Mon 1/22/07 | Tue 2/13/07 | |
| 34 | Initial setup, existing framework | 0% | 17 days | Mon 1/22/07 | Tue 2/13/07 | |
| 35 | Define proper CVS location for perl, libs, macros | 0% | 1 day | Mon 1/22/07 | Mon 1/22/07 | Jerome Lauret[10%],Andrew Rose[10%],Lee Barnby[10%] |
| 36 | Add existing QA macros to CVS | 0% | 1 day | Tue 1/23/07 | Tue 1/23/07 | Andrew Rose[20%] |
| 37 | Checkout and test on +1 site (non-PDSF), adjust as necessary | 0% | 1 wk | Wed 1/24/07 | Tue 1/30/07 | Lee Barnby[10%] |
| 38 | Bootstrap on +1 site / remove ALL site specifics references | 0% | 1 wk | Wed 1/31/07 | Tue 2/6/07 | Cristina Suarez[10%] |
| 39 | Commit to CVS, verify new scripts on all sites, final adjustments | 0% | 1 wk | Wed 2/7/07 | Tue 2/13/07 | Cristina Suarez[10%],Andrew Rose[10%],Lee Barnby[10%] |
| 40 | QA and nightly tests | 17% | 7 days? | Mon 1/22/07 | Tue 1/30/07 | |
| 41 | Establish a QA area in CVS | 100% | 1 day? | Mon 1/22/07 | Mon 1/22/07 | |
| 42 | Check existing QA suite | 0% | 1 wk | Wed 1/24/07 | Tue 1/30/07 | |
| 43 | ||||||
| 44 | Development | 0% | 62 days | Mon 1/22/07 | Tue 4/17/07 | |
| 45 | General QA consolidation | 0% | 10 days | Wed 1/31/07 | Tue 2/13/07 | |
| 46 | Gather feedback from PWG, add QA tests relevant to Physics topics | 0% | 2 wks | Wed 1/31/07 | Tue 2/13/07 | |
| 47 | Establish nightly test framework at BNL for embedding | 0% | 1 wk | Wed 1/31/07 | Tue 2/6/07 | |
| 48 | General improvements | 0% | 35 days | Mon 1/22/07 | Fri 3/9/07 | |
| 49 | Requirements study for an embedding request interface | 0% | 2 wks | Mon 1/29/07 | Fri 2/9/07 | Andrew Rose[10%],Jerome Lauret[10%] |
| 50 | Develop new embedding request form compatible with Drupal module | 0% | 4 wks | Mon 2/12/07 | Fri 3/9/07 | Andrew Rose[10%] |
| 51 | Test new interface, import old tasks (historical purposes) | 0% | 5 days | Mon 1/22/07 | Fri 1/26/07 | Andrew Rose[10%],Cristina Suarez[10%] |
| 52 | Distributed Computing | 0% | 20 days | Wed 2/14/07 | Tue 3/13/07 | |
| 53 | Use SUMS framework to submit embedding, establish first XML | 0% | 1 wk | Wed 2/14/07 | Tue 2/20/07 | Lee Barnby[10%] |
| 54 | Test on one site | 0% | 1 wk | Wed 2/21/07 | Tue 2/27/07 | Lee Barnby[10%] |
| 55 | Test on all sites, adjust as necessary | 0% | 2 wks | Wed 2/28/07 | Tue 3/13/07 | Cristina Suarez[10%],Andrew Rose[10%],Lee Barnby[10%] |
| 56 | Gridfication | 0% | 25 days | Wed 3/14/07 | Tue 4/17/07 | |
| 57 | Test XML using Grid policy (one site) | 0% | 1 wk | Wed 3/14/07 | Tue 3/20/07 | |
| 58 | Establish test of data transfer method, GSI enabled HPSS access possible | 0% | 1 wk | Wed 3/21/07 | Tue 3/27/07 | |
| 59 | Regression and stress test on one site | 0% | 1 wk | Wed 3/28/07 | Tue 4/3/07 | |
| 60 | Test on +1 site, infrastructure consolidation | 0% | 2 wks | Wed 4/4/07 | Tue 4/17/07 | |
| 61 | ||||||
| 62 | Embedding operation | 25% | 261 days? | Mon 1/1/07 | Mon 12/31/07 | |
| 63 | PDSF support | 50% | 261 days? | Mon 1/1/07 | Mon 12/31/07 | Andrew Rose[10%] |
| 64 | BHAM support | 10% | 261 days? | Mon 1/1/07 | Mon 12/31/07 | Lee Barnby[10%] |
| 65 | UIC Support including QA | 15% | 261 days? | Mon 1/1/07 | Mon 12/31/07 | Olga Barranikova[5%],Cristina Suarez[10%] |