The project is funded by RHIC and the Department of Energy as a
research and development program of the STAR collaboration. The RD phase
lasts from FY93 to FY95. The project is expected to convert into a
construction project by FY96. The proposed schedule will
allow completion of the SVT by the beginning of 1999, which coincides with
the RHIC turn-on.
The overall cost of the SVT program is
6.2 million dollars (including RD phase FY93-FY95). Up to 1.5 million
dollars are committed by the
Department of Energy to be spent during the R
D phase.
At the time of the STAR conceptual design report the SVT was already part
of the general cost and schedule breakdown of STAR.
Table 2 shows the cost breakdown for the main subsystems of the SVT
project based on the WBS (work breakdown schedule) number system developed
by STAR. The contributions of STAR and the DoE to the R+D phase (FY93-95)
are summarized in column 1. We assume an allocation of about $700 K in
RD money for 1995. A considerable shortfall in R
D money in the early
years of the project has lead to a moderate cost increase of the system
throughout 1998. For the construction phase we suggest a funding profile
which peaks in FY96 and FY97. All numbers are based on detailed engineering
estimates or vendor quotes, and include material cost, labor, EDIA, and
contingency (
30%).