hello ralph-thank you for the new plan....
we would like to remove tofr in the morning of 5/29 and
move it to the clean room. we can get it disconnected and ready
to slide out during the evening of 5/28... should take <20min.
does this cause any major conflcits?
also fyi on 5/27-28 i will be covering, rolling, and neatly stowing the
pvpd signal/HV cables (presently platform->balconies) so they will be out
of the way when you're ready to roll STAR.
i would also be happy to help remove/neatly stow the pVPD det assys from
around the pipe during this trip if this would be helpful to the schedule.
regards,
bill
At 11:21 AM -0400 5/13/03, Ralph L. Brown wrote:
>Folks,
>
>I have attached the latest version of the STAR FY03 Shutdown
>Schedule in both a project format (.mpp) and web viewable (.html). I
>have asked Penka to place this on the STSG website. I have the
>following comments:
>
>
>
>1) This plan includes the installation of an SSD detector,
>although a decision will be made the end of May. If the decision is
>not to install we will still remove both FTPC's in order to survey
>the location of the SVT cone, and then go directly into installing
>BEMC modules.
>
>2) I've included one day of subsystem testing in the WAH
>before we begin shutting down the detector.
>
>3) I ask all subsystems to make themselves available to
>disconnect there utility connections during the first week of the
>shutdown.
>
>4) Rework of the WAH overhead crane was removed due to lack of funding.
>
>5) Although it is not shown, C-AD will begin work on a new
>Control Room drop ceiling.
>
>6) Magnet and Power supply cooling water will be off, but MCW
>will be available for electronics.
>
>7) AC power will be available for electronics during the shutdown.
>
>8) The only new AC power installation work for electricians
>will be on the east side of the magnet for BEMC electronics.
>
>9) Please review and comment on any issues of the plan.
>
>
>
>I thank you for your inputŠŠŠ.Ralph
>
>
>
>Ralph L. Brown
>
>STAR Technical Support Group Leader
>
>Brookhaven National Laboratory
>
>Bldg. 1006C
>
>Upton, New York 11973
>
>Email: rlbrown_at_bnl.gov
>
>Office: 631 344-7775
>
>Cell: 631 255-4979
>
>Page: 8545
>
>
>
>
>Attachment converted: Mac8_D:Shutdown FY03 v4.mpp (MPP /MSPJ) (00012630)
>Attachment converted: Mac8_D:Shutdown FY03 v4.html (TEXT/MSIE) (00012631)
--W.J. Llope, Ph.D. Res. Assoc. Professor T.W. Bonner Nuclear Laboratory phone: 713-348-4741 Rice University, MS-315 fax: 713-348-5215 6100 S. Main St. Houston, TX 77005-1892 e-mail: llope_at_physics.rice.edu WWW home: http://wjllope.rice.edu/default.html
--
This archive was generated by hypermail 2.1.4 : Thu Jul 24 2003 - 00:39:42 EDT